I was trying to avoid having to go through each day on the programme setting up a chain of links through each and every element (72 columns, 170 beams, 520 roof slabs, and 40 capping beams!) in case of future methodology changes, but was hoping a combination of scheduling the first few columns to be installed (ie start at one end of site, working through to the other side), (with remaining elements “start as soon as possible”) and then resource levelling could work
Maybe a future improvement could be proximity-based resource levelling, where the nearest elements are given priority rather than the order they are selected in?